Per OMB eCFR §200.323, the University must negotiate profit as a separate element of the price for each contract in which there is no price competition and in all cases where cost analysis is performed. To establish a fair and reasonable profit, consideration must be given to the complexity of the work to be performed, the risk borne by the contractor, the contractor's investment, the amount of subcontracting, the quality of its record of past performance, and industry profit rates in the surrounding geographical area for similar work. A cost plus percentage of cost cannot be used.
Per FAR 15.404.4(c)(4):
(i) The contracting officer shall not negotiate a price or fee that exceeds the following statutory limitations, imposed by 10 U.S.C. 2306(d) and 41 U.S.C. 3905:
- (A) For experimental, developmental, or research work performed under a cost-plus-fixed-fee contract, the fee shall not exceed 15 percent of the contract’s estimated cost, excluding fee.
- (B) For architect-engineer services for public works or utilities, the contract price or the estimated cost and fee for production and delivery of designs, plans, drawings, and specifications shall not exceed 6 percent of the estimated cost of construction of the public work or utility, excluding fees.
- (C) For other cost-plus-fixed-fee contracts, the fee shall not exceed 10 percent of the contract’s estimated cost, excluding fee.
(ii) The contracting officer’s signature on the price negotiation memorandum or other documentation supporting determination of fair and reasonable price documents the contracting officer’s determination that the statutory price or fee limitations have not been exceeded